Your Fixed-Price Bid Was Right. The Job Changed.
A fixed-price job finishes, the money comes in, and somehow there's less left than there should be. The usual reaction is to blame the bid. "I priced it too low."
Sometimes that's true. More often the bid was fine for the job you bid. The job you actually did was a different one.
Two kinds of losses look the same on paper
When a job comes in under margin, it's one of two problems.
The first is an estimating problem. You missed something that was always part of the job, like a material you forgot to count or labor you underestimated. The fix is a better estimate next time.
The second is a scope problem. The customer asked for things that weren't in the bid, and you did them without pricing them. The fix there isn't a higher bid. It's billing for the extra work.
If you treat a scope problem like an estimating problem, you start padding every bid. Then you lose jobs you should have won, and the leak is still there.
A simple bid-versus-actual check
You can sort out which problem you have with one finished job and an hour at the kitchen table. You need three things: the bid or contract, your actual hours and materials, and every text, email, and note from the customer during the job.
Then go line by line.
- For each item in the bid, compare what you planned to what it actually took.
- For each extra hour or extra material, ask one question: was that part of the original job, or did the customer ask for something new?
- Mark each one "estimate" or "scope."
Here's a made-up example. You bid a bathroom at 60 hours. It took 78. Going line by line, 6 of the extra hours were demo that took longer than you planned. That's estimate. The other 12 were a moved outlet, a second paint color, and a towel bar the customer added. That's scope.
When you're done, add up both columns. That tells you whether you need to bid differently or bill differently. A lot of the time, the second column is the bigger one.
Why the second column is easy to miss
Scope changes rarely come in as one big request. They come in as small asks in a text on a Tuesday. "Can you also..." "While you're here..." Each one is a few minutes or a few hundred dollars. None of them feel worth writing up at the time.
I spent about 25 years in food service before I started building food trailers. In both, the money rarely went out in one big mistake. It went out in small pieces nobody wrote down.
Fix it on the next job, not the last one
Once you know where the money went, the fix is plain. Write the scope so it says what's out, not just what's in. Price changes before the work starts. Keep every approved change in one place so billing is adding up a list, not scrolling through your phone.
A tool that keeps the changes in one place
Parallax Media Group builds simple tools that do one job. Our first one is ScopeGuard, a phone tool for getting extras signed before you do the work.
You type the change and the price on your phone. Your customer gets a link, reads it and signs with a finger, no account needed. You end up with a signed PDF and a running total for the final bill. Signature reminders are rolling out to founding shops, and texting is coming soon.
Pro is $29/month. Founding shops get 60 days free, then $15/month locked for life. If you've ever finished a fixed-price job and couldn't say where the margin went, start with joining the founding shops.
Ryan Burnett, Founder, Parallax Media Group