Stop Raising Every Bid Until You Check One Finished Job

A job finishes under margin. The next move for a lot of owners is simple: raise every bid.

Sometimes that is the right call. Often it is the wrong one. You end up losing jobs you should have won, and the leak that cost you money on the last job is still open on the next one.

Before you change your price sheet, check one finished job. Separate what you estimated wrong from what you never billed.

Two problems look the same in the bank account

Estimating problem: something that was always part of the job took more hours or more material than you planned. Fix: better takeoffs, better labor assumptions, clearer allowances.

Scope problem: the customer asked for work that wasn't in the bid, and you did it without a priced approval. Fix: write changes down and bill them before the work starts.

If you treat a scope problem like an estimating problem, you pad the number and hope. Hope is not a system.

One job, one hour, three piles

Pull a recent fixed-price job. You need the bid or contract, your actual hours and materials, and the customer messages from the job.

Make three piles:

  1. In the bid, and it ran as planned. Leave these alone.
  2. In the bid, but it took more than you thought. That's estimating. Note the miss so the next similar bid is tighter.
  3. Not in the bid. Texts, walkthrough adds, "while you're here" items, owner-supplied fixes. That's scope. Note whether you billed each one.

You don't need software for this. A printed proposal and a highlighter will do.

When pile three is bigger than pile two, raising every bid won't fix your year. Billing the next pile three will.

What pile three usually looks like

Small asks. Fast yeses. No price attached.

A moved outlet after the wall was closed. A second finish color. Matching existing trim farther than you planned. Waiting on an owner-supplied fixture, then making a second trip. Punch-list items that were never in the original scope.

Each one felt too small to stop for. Together they ate the margin.

I spent about 25 years in food service before I started building food trailers. In a kitchen and on a jobsite, the money rarely leaves in one dramatic mistake. It leaves in pieces nobody wrote down.

Fix the next job, not your whole price list

Once you know which pile hurt you, the next step is plain.

If estimating missed, update that line item on the next similar bid. Don't multiply a bathroom miss across every service you offer.

If scope missed, change the habit: short written change (text is fine) with a price, get a yes, then start. Put a couple of lines in the next contract so the mid-job text isn't a surprise.

Raising prices across the board is easy. It also hides which problem you actually have.

A one-job tool for the extras you keep skipping

Parallax Media Group builds simple tools that do one job.

Our first product is ScopeGuard. It's a phone tool for fab and trade shops: you type the change and the price, the customer signs from a link, and you get a signed PDF before the extra work starts. Signature reminders are rolling out to founding shops, and texting is coming soon.

Pro is $29/month. Founding shops get 60 days free, then $15/month locked for life.

If you've been tempted to raise every bid after a thin job, check that job first, then use a tool that gets the next extras signed. Start with ScopeGuard's founding shops.

Ryan Burnett, Founder, Parallax Media Group